# Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States

Speed-to-power, not energy price, decides how AI data centers should get power

Alex C. Newkirk, Daniel L. Gerber, Erica R. H. Fuchs, Alex Hubbard, M. Granger Morgan, Arman Shehabi and 2 more · arXiv · 2026-11-12

- **Problem** Grid interconnection queues and gas turbine backlogs delay AI data centers by years. Energy cost comparisons ignore the GPU compute lost while a facility waits to be built.
- **Method** The authors add the value of compute lost during construction to each option's levelized cost of energy. Options are ranked by that speed-adjusted sum across U.S. locations.
- **Results** DC-coupled solar becomes the lowest-cost option in 84.9% of U.S. locations once lost compute is counted. Without that adjustment, grid interconnection usually wins on energy cost alone.

![Figure 1: Analytical framework.For a given quantity of chips, workload (in this research empirically calibrated to AI training) and location (climate, solar re…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-a7273e30e1707baf7e53dd2f126bac09.png?thumb=512)

**Figure 1** : Analytical framework.For a given quantity of chips, workload (in this research empirically calibrated to AI training) and location (climate, solar resource, gas price, grid rate, and interconnection queue), we build an hourly facility load combining IT demand with climate-driven cooling (PUE). We then size and dispatch three islanded architectures, AC solar+storage, DC solar+storage, and islanded natural gas with diesel backup, and compare them against grid interconnection. Each deliver equivalent energy service at equivalent reliability through an explicitly modeled power-conversion path. Each option is assessed on two axes: its unadjusted levelized cost of energy ($/kWh) and the value of compute forgone during construction (set by deployment speed and chip-hour value). Their sum, a speed-adjusted cost (LCOEadj), determines the preferred option, which varies with location, scale, technology, and the value of time.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/) · Alex C. Newkirk, Daniel L. Gerber, Erica R. H. Fuchs, Alex Hubbard, M. Granger Morgan, Arman Shehabi, Sarah J. Smith, Constantine Samaras · Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States · Original paper figure · Extracted the figure area from page 5 of the original PDF.

## Why power timing now outweighs power price

AI data centers now run at the scale of hundreds of megawatts, and some announced projects reach the scale of gigawatts. Firms want this capacity fast, because they prioritize deployment speed over other considerations to avoid falling behind competitors. The legacy electricity system moves much more slowly than this urgency, since utility planning and permitting were built for nearly two decades of flat consumption.

Grid interconnection queues, the delay before large loads can connect, are rising and exceed 5 years in some regions. Equipment adds to the delay, because grain-oriented electrical steel, grid transformers and high voltage circuit breakers often have multi-year backlogs. Firms respond by signing exclusive power purchase agreements, and some build their own power, operating partially or fully islanded from local grids.

For these firms, the question is therefore less about the cheapest kilowatt-hour and more about which power source is ready first.

Waiting has a direct cost, because each month of construction is a month of GPUs that produce no output. That work didn't price speed against energy cost across architectures, and the paper's own framework fills that gap. The DC versus AC question for solar and storage was studied separately from data centers, and no work had combined the two.

To value this delay, the authors price the compute forgone during construction at the $2.40/GPU-hour H100 rental index price. This rental price is the floor utility of the marginal GPU-hour, because an operator who can't earn at least this value should rent compute to the market. Eq. 1 sums the idle GPU-hours in each pre-operational year, multiplied by the number of GPUs and the spot price.

Because this value enters the cost during construction, a standard levelized cost, which counts only costs and delivered energy, can't see the delay.

## A speed-adjusted cost for each option

The speed-adjusted cost adds the value of compute lost during construction to each option's levelized cost of energy, then ranks the options by that sum. Each option therefore carries two numbers: an unadjusted LCOE in $/kWh and a forgone-compute value set by how long the option takes to build.

The forgone value is built year by year, multiplying the idle GPU-hours in each pre-operational year by the spot rental rate and the GPU count. The authors price each idle GPU-hour at $2.40, the H100 rental index price in year-0 dollars. That rate works as a floor, because a firm training frontier models may value a GPU-hour well above its rental price.

For firms running only proprietary training, the spot price likely understates the value of compute.

LCOEadj divides the discounted sum of capital, operating and lost-compute costs by the discounted sum of delivered energy. Both sums use a 7% base-case discount rate with mid-year discounting, and n is the evaluation year shared by every scenario. Solar-plus-storage systems follow a 24-month construction timeline, so their lost-compute term stays short.

Grid interconnection uses each state's 2018-2023 median queue duration, so a 5-year wait costs 3 years of operation against 2-year solar construction.

To test how robust the ranking is, the authors vary the GPU value from $1.00 to $4.00 per hour. They also shift the construction timelines by ±50%, then check whether the selected architecture changes.

## Four supply paths built to the same load

The load is a fleet of 8-H100 node equivalents with an average draw of 7.3 kW and a maximum of 8.5 kW. A 100,000-GPU facility therefore has a design load of about 131 MW, and the power systems are sized to that peak. Cooling enters through hourly PUE from Lei and Masanet's framework, using the minimum annual PUE for the location. Power systems are sized to the maximum IT load times the 99th percentile PUE and a 1.05 contingency factor.

Every path must meet the load in 99% of hours, and the remaining hours count as unserved.

PV panels make DC power, so the AC design needs an inverter and a transformer before the grid can take the output. In the AC design, storage shares the PV inverter, while in the all-DC design it is centralized off the ±10 kV spine. The all-DC medium-voltage layout steps 1500 V DC blocks up to ±10 kV for the campus, then steps down within the data hall to a ±400 V bus.

The AC layout instead distributes power at 34.5 kV and then 480 V AC, the conventional path that grid and gas plants also use. Figure 2 shows these candidate medium-voltage power-flow paths with their modeled component efficiencies.

The battery is a 4-hour LFP system built from 60 MW packs that store 240 MWh, and dispatch sends surplus solar to the battery before any curtailment. Degradation follows BLAST-Lite for LFP and a linear solar fade of 1% in year one and 0.55% a year after that. Battery replacement happens once, at year 13, while the PV modules have a 25-year life and the model runs to year 27.

Gas plants choose from 16 reference turbines, with part-load penalties and ambient derating included. Backup diesel covers minimum facility power, sized to match the gas plant's expected unserved energy.

Turbine delivery at 36 months can limit the gas timeline, because 30% of construction waits on it. Grid interconnection uses each state's 2018-2023 median queue duration from supply-side data.

## DC coupling saves on hardware, not on rates

On average, the all-DC design runs about 18% cheaper than its AC counterpart, close to 9 cents per kWh. In the Permian Basin, a 100,000-GPU facility of about 131 MW gets energy at $0.27/kWh from the all-DC microgrid. The AC system costs $0.33/kWh for the same load, so the gap works out to $0.062/kWh. The authors trace the gap to avoided hardware, namely eliminated inverters and higher path efficiency.

The DC advantage shifts from site to site, since the share of energy flowing directly from PV to load differs. Across the 5th to 95th percentile range, levelized cost spreads by roughly $0.40/kWh within each PV architecture. The worst five-day insolation window explains this spread better than annual sunlight does. A dry interior-West Colorado site comes in at $0.21/kWh, while a fog-prone northern-California site reaches $0.61/kWh.

Natural gas behaves differently, because its costs fall as facility capacity grows. Small aeroderivative plants at 10 to 20 MW reach $0.25 to $0.30/kWh. In eastern Colorado at $7.70/MMBTU, gas reaches cost parity with DC microgrids near 30 MW. A higher gas price moves this crossover toward larger facilities, while cheaper gas pulls it toward smaller ones.

Gas costs drop by $0.15/kWh across the range of system scales plotted in Figure 4.

PV+BESS costs barely move with nameplate capacity, staying within ±$0.002/kWh. Low-voltage layouts cut costs by a median 2.4% for DC and 3.7% for AC against medium-voltage counterparts.

## Counting lost compute changes the winner

Once lost compute enters the cost, DC-coupled solar becomes the lowest-cost option in 84.9% of U.S. locations. Without that speed adjustment, grid interconnection generally beats the microgrids on unadjusted LCOE. The speed edge comes from a 24-month solar-plus-storage build, while grid interconnection can take 4 to 5 years. Lost compute is priced as idle GPU-hours multiplied by a spot rental rate of $2.40 per GPU-hour.

Grid connection wins in Maine, where the nation's fastest interconnection timeline offsets moderate electricity prices. NYISO's longer interconnection queue makes DC solar preferable in upstate New York, despite moderate utility rates. East Texas and Georgia each pair industrial electricity below 6¢/kWh with three-year interconnection. Gas rarely wins, because gas prices and grid electricity costs tend to move together in most markets.

When gas turbine microgrids come online after three years, the split becomes 55.6% DC solar, 35.2% natural gas, and 9.2% grid. DC solar keeps a majority of U.S. locations even under that accelerated gas timeline, which assumes 36-month turbine delivery. Lost compute also sets an indifference threshold: the chip-hour value at which a firm is indifferent between DC microgrids and grid interconnection.

That threshold falls below $1.00/hr in high-insolation regions and rises above $4.00/hr in solar-poor locations. The median is $1.61 per chip-hour, under the $2.40/hr baseline.

Reliability adds value too: moving from 90% to 99% uptime is worth about $0.20/kWh in avoided lost compute. The step from one to two nines clears the threshold in every DOE climate zone tested except Seattle, WA. They didn't find that compute value alone justifies moving to 99.9% uptime at any location.

## Which assumptions move the answer

Solar costs climb with availability, because each extra nine of uptime requires more installed capacity. Gas costs move the other way, since fixed capital spreads over more operating hours at higher utilization. The authors compare this to macro grids, where infrastructure is scoped for the worst-case scenario.

For fixed designs, gas cost is driven mainly by fuel price rather than by discount rate or capital cost. Across the continental U.S., from Oklahoma to California, gas cost spreads by $0.08 to $0.11/kWh. Solar plus storage cost responds most strongly to the discount rate, varying 27% to 43% across rates of 3% to 12%. Land cost is negligible; it would need a sixfold increase to match battery O&M, the next lowest influence.

Only facilities of 180 MW or more in high-fuel-price regions adopt combined cycle, which can hedge fuel-price risk.

Internal power-system choices change LCOE less than the choice of architecture does. Routing the full IT load through online double-conversion adds about 5.9% to base LCOE, or 6.4% when cooling is also conditioned. The all-DC advantage splits into a path-efficiency part near 7.9% and a roughly equal avoided-capital part.

The authors size systems on typical meteorological year data, which they call a mildly optimistic sizing basis. Re-optimizing against each historical year from 2010 to 2023 puts TMY-based designs a median 4.5% ($0.012/kWh) below the historical mean. Stitched typical months tend to trim the worst stretches, so the designs may modestly undersize solar plus BESS.

Propagating each state's historical price dispersion through a committed gas plant moves LCOE within $0.005 to $0.024/kWh, with a median of $0.011/kWh.

## Where the numbers stop applying

The grid case is best read as a floor, because the model leaves out some costs that large loads can trigger. Utilities usually pay these costs but recover them through rates, which shifts part of the bill onto other ratepayers. Interconnection timing uses regional median supply-side queue durations from \[13\] as a proxy for large-load requests.

State-level aggregation hides intrastate differences in queue congestion, and demand-side requests may move differently from supply-side ones.

The design relies on typical meteorological year data, which the authors call a mildly optimistic sizing basis. Re-optimizing on each year from 2010 to 2023 puts TMY a median 4.5% ($0.012/kWh) below the historical-year mean. Single-location TMY datasets mean neighboring sites with similar climates can diverge, especially where spatial climate varies sharply.

The DC design assumes mature supply chains that, in some cases, don't yet exist at scale. Integrated performance at 100+ MW still needs empirical validation, since the component values come from datasheets.

The 9¢/kWh average DC advantage is an expected value, so early projects may capture only partial gains. Trade or geopolitical disruptions to PV modules or LFP cathodes would delay deployment, and the model doesn't include them. Natural gas uses state-level industrial prices as uniform proxies, so a facility near a pipeline hub may face lower costs.

The authors didn't model nuclear, advanced geothermal, wind, reciprocating engines or mixed portfolios, leaving them to future work. The uptime target treats the load as non-reactive, so it serves as a conservative lower bound on achievable reliability. Battery residual value is left out, even though modules at mid-scenario replacement keep 89% state-of-health on average.

## Paper info

- **Authors**: Alex C. Newkirk, Daniel L. Gerber, Erica R. H. Fuchs, Alex Hubbard, M. Granger Morgan, Arman Shehabi, Sarah J. Smith, Constantine Samaras
- **Venue**: arXiv · Preprint
- **First published**: 2026-11-12
- **Added**: 2026-11-14
- **Updated**: 2026-11-12
- **Version**: v1
- **arXiv**: 2611.17098
- **Category**: cs.AI · eess.SY
- **Original paper terms**: [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)
- **What we show**: Paper info, commentary and permitted figures from the original paper

[Original paper ↗](https://arxiv.org/abs/2611.17098v1) · [PDF ↗](https://arxiv.org/pdf/2611.17098v1)

AI commentary is a separate explanation from the original paper and may contain errors. The original paper and figures follow each source's terms of use and any rights noted separately.

## Abstract

The rapid growth of artificial intelligence is driving demand for new data centers at large scale and on short deployment timelines. To power them, firms connect to the commercial grid or contract generation directly, but interconnection and gas-turbine delays now incentivize on-site generation. We compare grid-connected and off-grid data center energy infrastructure (AC- and DC-coupled solar-plus-storage, islanded natural gas, and grid interconnection) across the continental U.S. Using an open-source technoeconomic framework built on empirically calibrated AI training loads, climate-driven cooling, stage-by-stage power conversion, and physics-based battery degradation, we model designs providing equivalent energy services. Our central contribution is a speed-adjusted cost of energy that values the compute unlocked by faster construction, making options with different deployment timelines directly comparable on one physically consistent basis. We find DC coupling reduces lifetime energy costs by 18% ($0.09/ kWh) on average versus AC counterparts by eliminating inverters and improving efficiency. Though rarely cheapest on unadjusted energy cost, DC-coupled microgrids' faster deployment makes them the lowest-cost modeled option in 85% of U.S. locations once foregone compute is valued, or 55% under accelerated natural gas timelines. For AI infrastructure, deployment speed rather than unit energy cost determines the economically preferred path to power.

## Figures from the paper

![Figure 2: Candidate MV power flow models within the facility fence-line with modeled component efficiencies.Power flows are idealized, without batching or corr…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-3bcbb0afa9796aa9b45200e83c472caa.png?thumb=512)

**Figure 2** : Candidate MV power flow models within the facility fence-line with modeled component efficiencies.Power flows are idealized, without batching or correspondence to any particular facility scale. Grid power and islanded natural gas are assumed to have equivalent power systems architecture inside the facility fenceline. Note that while not shown on the plot, the diesel backup power for the grid comparison and islanded natural gas cases is modeled as entering the facility through the same main power distribution path. Fault protection components, monitoring components, or supercapacitor banks are not shown. BESS and UPS components are shown abstracted from the facility layout and composition, and may in practice be centralized for the facility, distributed at the sidecar, rack, or node level, or some combination. Microgrids that use BESS for backup substitute these assets for the UPS via a small share of capacity embedded in the LV data hall (see Supplementary Information). AC power systems distribute power at 480 V bus voltage, with embedded PSU or motor drive power electronics converting to the voltages required by IT and HVAC loads. Bidirectional grid-forming inverters convert the DC outputs to AC at the specified bus voltage and frequency. DC power systems operate at a±400 V DC bus voltage, with DC-DC converters stepping up to bus voltage and PSUs and ESCs stepping down to deliver the required load voltages.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

![Figure 3: Cost advantage of DC-coupled systems over AC counterparts for 100,000 GPUs at 99% uptime across all modeled continental U.S. locations.Skew in the ab…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-7299b2fcb245919a7ad9fe6ca5e24e50.png?thumb=512)

**Figure 3** : Cost advantage of DC-coupled systems over AC counterparts for 100,000 GPUs at 99% uptime across all modeled continental U.S. locations.Skew in the absolute distribution reflects variation in sensitivity to solar-to-load and battery-to-load path efficiency by location. Scale of DC advantage generally increases in locations with lower quality solar resources as marginal path efficiencies provide returns for highly overbuilt systems. In regions with substantial and consistent solar resources, both AC and all-DC microgrids can scope more aggressively, shrinking but not eliminating the DC cost advantage.(A)Percentage cost advantage distribution. Mean DC advantage is 18% of total cost of ownership for a given location.(B) Absolute cost advantage distribution. Mean DC advantage is $0.09 / kWh.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

![Figure 4: LCOE of the minimum cost natural gas configurations against different facility design loads at 99% uptime in eastern Colorado; natural gas price of $…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-f12b1c542a5f1acf0f7afb91403f2881.png?thumb=512)

**Figure 4** : LCOE of the minimum cost natural gas configurations against different facility design loads at 99% uptime in eastern Colorado; natural gas price of $7.70 / MMBTU.Points correspond to the LCOE for a given design, with color indicating turbine class (coral for aeroderivative, teal for F-class) and shape indicating single cycle (SC) or combined cycle (CC) configuration. Step-sizes between points are increments of 2 MW of design load up from 1-20 MW, 4 MW of design load from 20-64 MW, and 8 MW of design load from 64 MW to 320 MW. Dashed lines indicate the LCOE of medium-voltage DC (green) and AC (yellow) PV+BESS systems at the same location. Natural gas plants exhibit significant scale economies, dropping by$0.15/ kWh over the range of system scales. PV+BESS systems showed minimal unit cost variation with nameplate capacity(±$0.002/ kWh), we plot these costs as idealized average values without this noise for visual clarity. Jaggedness on the natural gas curve demonstrates transitions between turbine models and classes, and plant configurations as data center facility scale changes.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

![Figure 5: Annual utilization requirements determine optimal power architecture across diverse geographic and market conditions.Each panel shows levelized cost…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-aa9abe77e738da3b5509b1452a23a8ad.png?thumb=512)

**Figure 5** : Annual utilization requirements determine optimal power architecture across diverse geographic and market conditions.Each panel shows levelized cost of electricity versus annual share of energy-service-hours provided by the islanded microgrid for a 100,000 GPU datacenter, comparing MV DC-coupled solar (blue), natural gas with diesel backup (orange), and the grid comparison case (gray dashed). The horizontal axis reads two ways: the annual uptime of a fully islanded facility, with the remaining hours unserved; or the fraction of hours an otherwise grid-tied facility runs on its microgrid. Solar architectures at low utilization are constrained by power capacity rather than energy, meaning costs initially decline as utilization increases. Natural gas costs decline monotonically as fixed capital is amortized over more operating hours. Facility design loads vary by location due to location-specific cooling system performance. (A) Southeastern California: Exceptional solar resources and high electricity prices ($0.185/kWh) favor DC solar across all utilization levels. (B) Houston, Texas: Natural gas becomes less expensive than DC solar above 77% annual uptime, though both exceed grid costs ($0.055/kWh). (C) Northern Virginia: Data center alley. (D) Eastern Washington State: Solar resource inconsistency makes high reliability with PV+BESS systems expensive. The hitch in natural gas at higher utilization reflects transition to an alternative plant configuration at higher uptimes.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

![Figure 6: Minimum speed-premium LCOE for 100,000 GPU facilities across the continental United States.Color indicates LCOE magnitude; hatching shows lowest-LCOE…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-5ee8d7155ab251e87383bfcb21125461.png?thumb=512)

**Figure 6** : Minimum speed-premium LCOE for 100,000 GPU facilities across the continental United States.Color indicates LCOE magnitude; hatching shows lowest-LCOE adj technology. Maps vary by natural gas deployment speed assumptions, with the top panel (A) showing the baseline case of 4 year combined turbine delivery and plant construction time, and the bottom panel (B) showing the accelerated 3 year case.(A)Baseline construction timelines: DC solar is the lowestLCOE adj architecture in 85% of locations due to rapid deployment despite higher unadjusted energy costs. Grid interconnection remains preferred in regions (15% of locations) combining poor solar resources, low industrial electricity rates, and abbreviated approval timelines.(B)Accelerated 36-month natural gas timelines: DC solar (solid) is preferred in∼55% of locations. Natural gas (dots) is preferred in∼35% of locations, forming coherent regional deployments in solar-poor areas (upper Midwest, Appalachian Basin, Pacific Northwest). Grid interconnection (diagonal hatching) remains optimal in∼9% of locations. Even under this aggressive scenario, DC solar microgrids remain the most widely preferred option.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

![Figure 7: Value of a chip-hour at which firms would be indifferent between DC-coupled microgrids and grid interconnection.Holding interconnection timelines at…](https://refivu.com/papers/59c862ce-9112-44ef-844c-60828dd3cb56/figures/figure-1db8c3c75b8b60085d948d26f9e695b9.png?thumb=512)

**Figure 7** : Value of a chip-hour at which firms would be indifferent between DC-coupled microgrids and grid interconnection.Holding interconnection timelines at baseline (state-specific, 2.5-5 years). Color indicates indifference utility in $/GPU-hour; white contour marks the baseline assumption ($2.40/hr). Blue regions show where DC solar dominates even at low GPU values due to favorable solar resources and/or slow grid interconnection. The median indifference utility is $1.61/hr. Orange/red regions (concentrated in New England and parts of Texas) show where grid remains competitive even at high GPU opportunity costs due to cheap electricity and fast interconnection. Most of continental U.S. lies below $2.40/hr (blue spectrum), indicating DC microgrids are preferable to grid interconnection when valuing deployment speed even at lower GPU value.

[Original paper](https://arxiv.org/abs/2611.17098v1) · [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/)

## Quote from the paper

Alex C. Newkirk, Daniel L. Gerber, Erica R. H. Fuchs, Alex Hubbard, M. Granger Morgan, Arman Shehabi, Sarah J. Smith, Constantine Samaras (2026). Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States. arXiv:2611.17098v1. https://arxiv.org/abs/2611.17098v1

**BibTeX**

```
@misc{newkirk2026speed,
  title = {{Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States}},
  author = {Alex C. Newkirk and Daniel L. Gerber and Erica R. H. Fuchs and Alex Hubbard and M. Granger Morgan and Arman Shehabi and Sarah J. Smith and Constantine Samaras},
  year = {2026},
  eprint = {2611.17098},
  archivePrefix = {arXiv},
  url = {https://arxiv.org/abs/2611.17098v1}
}
```

## Other paper commentary

- [Bellman Contraction under MMD: A Unified Framework](https://refivu.com/en/papers/bc47e65f-4140-46f1-829a-ce2a7aea1312-bellman-contraction-under-mmd-a-unified-framework.md)
- [Tokenization: Hardness and Bicriteria Approximation Algorithms](https://refivu.com/en/papers/1f62be8b-f2d0-4aa2-b1ed-52835980285d-tokenization-hardness-and-bicriteria-approximation.md)
- [When Does Learned Constraint Selection Pay in Security-Constrained Optimisation? A Boundary Map from SCOPF to Unit Commitment](https://refivu.com/en/papers/bffeb870-d297-4786-a31b-cd7ba9c9f25e-when-does-learned-constraint-selection-pay-in-security.md)
- [Posterior contraction rates for banded approximations of Gaussian processes](https://refivu.com/en/papers/39b2feed-2c3a-4f79-b50f-498773f8d0d9-posterior-contraction-rates-for-banded-approximations-of.md)
- [When and How SignSGD Outperforms SGD: A Functional Scaling Law Perspective](https://refivu.com/en/papers/717fcb11-77f4-44a2-bdd6-2f8dee82543d-when-and-how-signsgd-outperforms-sgd-a-functional.md)
- [RESYNC: Residual Latent-State Synchronization for Deadline-Bound Streaming Inference](https://refivu.com/en/papers/93a3887b-d2df-450c-a06e-e64cb60d4325-resync-residual-latent-state-synchronization-for-deadline.md)
- [Near-Optimal Regret for Oracle-Efficient Adversarial Contextual Bandits](https://refivu.com/en/papers/59c9377d-a911-4ec5-acfc-c9189a7a8655-near-optimal-regret-for-oracle-efficient-adversarial.md)
- [AgentSSL: Can MLE Agents Leverage Unlabeled Data?](https://refivu.com/en/papers/7ba356fa-3652-4ea1-a299-cdcb8ac47ade-agentssl-can-mle-agents-leverage-unlabeled-data.md)
- [AeroZoo: A Benchmark of Well-Posed Flow Problems for Foundation Models of Aerodynamics](https://refivu.com/en/papers/ccdded95-ff8e-42fb-9bf0-b94e2c70922f-aerozoo-a-benchmark-of-well-posed-flow-problems.md)
- [ISLA: A Coordinate-Free, Measure-Weighted Transformer for Boundary-Driven PDEs](https://refivu.com/en/papers/cad1a674-b436-4a8f-938b-2889df82d40e-isla-a-coordinate-free-measure-weighted-transformer-for.md)
- [LazyWeights: Decode-on-Demand Edge LLMs](https://refivu.com/en/papers/e6b6c3c4-1bd3-46cf-8fce-73c9b9bbe83d-lazyweights-decode-on-demand-edge-llms.md)
- [CapLite: Prompt-Injection Defense for Small Language Model Agents without Model-Written Security Artifacts](https://refivu.com/en/papers/960c67c8-5daf-4bf3-b6e9-64d4b7a65f38-caplite-prompt-injection-defense-for-small-language-model.md)

---

AI-written text can contain mistakes. [Refivu](https://refivu.com/en/papers/59c862ce-9112-44ef-844c-60828dd3cb56-speed-to-power-dominates-energy-costs-for-ai)